What to Expect During Installation
A transparent, step-by-step guide to your solar installation journey from quote to commission
Installation Timeline
From quote to fully operational system: typically 3–4 weeks
Quote & Contract
Day 0-3
Permits & Approvals
Day 4-10
Installation
Day 11
Inspections
Day 12-14
Grid Connection
Day 15-25
System Active
Day 26+
Detailed Installation Process
A transparent breakdown of what happens from your first consultation through system activation.
Initial Consultation & Quote
Free on-site assessment of your property
- Site inspection and roof assessment
- Review electricity bills
- Discuss energy goals
- Detailed quote with rebates
- Answer all questions
Quote Review & Contract Signing
Review proposal and finalize system design
- Review component specifications
- Confirm layout and size
- Clarify warranties
- Sign contract
- Complete rebate paperwork
What to Expect on Installation Day
A smooth, professional installation process with minimal disruption to your daily routine.
On Your Property
- Installation crew of 2-4 technicians
- Work near roof & switchboard
- Minimal disruption
- Power off for 2-4 hours
- Site left clean
Roof Work
- No walking required
- All penetrations sealed
- Roof warranty maintained
- Safety harnesses used
- Minimal visible changes
Installation FAQs
How long does installation take?
Most residential systems take 6-8 hours and are completed in a single day.
Will I need to be home?
Yes, someone should be present for access and handover training.
What if weather is bad?
We reschedule at no extra cost if weather conditions are unsafe.